SDOT to Resume Paving on SW Genesee Street, 47th to 51st
Tue, 06/15/2010
Seattle Department of Transportation (SDOT) paving crews have been resurfacing SW Genesee Street from 47th Avenue SW to 49th Avenue SW. They recently completed grinding the old asphalt surface on these two blocks.
Today the crews have been given the “go ahead” to add two additional blocks of Genesee Street to the project, from 49th Avenue SW to 51st Avenue SW. The crews now plan to grind the old surface off of the additional blocks Wednesday (tomorrow), Thursday, and possibly also on Friday. They plan to lay the new asphalt, weather permitting, on Monday and Tuesday, June 21 and 22. One lane of traffic in each direction will remain open.
Genesee Street was not on SDOT’s original list of paving for 2010, but cost savings by the department from other paving projects have enabled SDOT to pave the street this year.