Delridge Way SW & SW Holden Street intersection will close May 31 - June 3
Thu, 05/23/2013
Information from SDOT
Most of the intersection of Delridge Way SW and SW Holden Street will be closed from 7 p.m. Friday, May 31, until 6 a.m. Monday, June 3, for roadway restoration and storm drain installation. This work is part of the Seattle Department of Transportation’s Delridge Way SW Paving Project that is rebuilding much of Delridge Way SW between SW Orchard and SW Roxbury streets.
For the closure of the Delridge/Holden intersection, the detour will be as follows (see attached map):
· Northbound traffic on Delridge Way SW - Take SW Thistle Street to 35th Avenue SW to SW Morgan Street/ Sylvan Way SW/ SW Orchard Street to Delridge Way SW
· Southbound traffic on Delridge Way SW - Take SW Holden Street to 35th Avenue SW to SW Thistle Street to Delridge Way SW
During the week of June 3, the roadway will be striped between SW Henderson and SW Thistle streets, the areas of Phases 1 and 2. Street parking will be eliminated and lanes will be temporarily shifted for up to four days while striping is completed.
This is a five-phase project. Upon completion of Phase 3 work, construction activity will move north to Phase 4, between SW Holden and SW Orchard streets. The Delridge Way SW Paving Project is funded by the “Bridging the Gap” transportation levy approved by Seattle voters in November 2006. Please visit the project website for more information: www.seattle.gov/transportation/pave_delridge.htm