SDOT: West Seattle Bridge weekly update April 29; High bridge repair: More progress on post-tensioning structural concrete; additional maintenance underway | Westside Seattle
Skip to main content
SDOT: West Seattle Bridge weekly update April 29; High bridge repair: More progress on post-tensioning structural concrete; additional maintenance underway
SDOT: West Seattle Bridge weekly update April 29; High bridge repair: More progress on post-tensioning structural concrete; additional maintenance underway
After the forms are removed from each structural component, the concrete will continue to cure for another 3 to 4 weeks before they tighten the cables. SDOT photo
Fri, 04/29/2022
Information from Seattle Department of Transporatation
We’ve completed the third structural concrete pour for the new post-tensioning system. While we prepare for more pours in May, we’re also removing the wooden forms from the concrete we poured the last few weeks now that it’s solid. After the concrete fully sets or “cures” for about a week, the forms are ready to come off.
Check out our time lapse video linked below to see the form removal process in action.
We also made progress on major maintenance work for the West Seattle Bridge this week. This work included preparation for the replacement of overhead signage and more expansion joints on the bridge.