Seattle Public Schools Building Excellence III Program has released another update on the construction of the co-joined Denny MIddle School and Chief Sealth High.
"Last month, the Project 1 contractor completed the retaining wall along the east property line as well as continued work on the sewer line along with east property. Grading for the north parking lot was started and will be completed by the first week of August.
This month, August, work for Project 1 will include site asphalt paving at the north parking lot and east road.
For Project 2, installation of the short aggregate piers will be completed by the end of this month. The Project 2 contractor is starting the interior renovation of the main classroom building for Chief Sealth. Foundation work will also be starting in August along with site work including grading, excavation and underground utilities for the new Denny school.
Installation of some storm sewer piping and connecting to the existing sanitary manhole in Southwest Kenyon Street, 260 feet east of the Southwest 26th Avenue intersection will take place Aug. 10 through 21.
The new utility will serve the new Denny Sealth campus scheduled to open in fall, 2010. No other utilities will be impacted by this work. Pedestrian and vehicle access to homes adjacent to the work zone will be maintained during the street closure. Detour signs will be up to direct all other traffic during construction hours.
Please contact the Denny/Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.
Please note - For safety reasons, visitor access is not permitted on the construction site at this time."
Project timeline:
Fall 2010 – Modernized Chief Sealth High School Opens
Winter 2011 - New Denny International Middle School Opens
Summer 2011 – New Community/Sealth Fields Open