The Seattle Department of Transportation has completed paving the west side of Greenwood Avenue North from North 105th to North 112th and will begin demolition and paving on the eastside of the street the week of Sept 14.
Work will start at North 105th and move northward. One lane of traffic in each direction will be open 24 hours a day, seven days a week through the end of October.
There will be no on-street parking in the work zones, and access to driveways may be temporarily restricted. Emergency access will be maintained.
Improvements to Greenwood Avenue North include: new pavement, sidewalks, street trees and lighting.
For information: calll George Frost at (206) 615-0786 or visit the project Web site.