Information from District 1 City Councilmember Lisa Herbold
Construction is anticipated to begin the first week of April on the Terminal 5 Quiet Zone. Design was completed in January 2023.
You can sign up for project updates here.
My office requested an update on the shore power infrastructure at Terminal 5, which allows a vessel to plug into electricity while at berth, substantially reducing air emissions.
The Northwest Seaport Alliance (NWSA) reports to our office that the shore power component of their Terminal 5 Modernization program remains under its commissioning phase. They shared a reminder that this is the first international cargo facility in Puget Sound to install a shore power system and has proven to be a complicated technical endeavor. NWSA staff committed to keep us informed as the testing phase continues and expects to share another update within the next few weeks.