map courtesy City of SeaTac
information from the City of SeaTac
Military Road South and South 152nd Street
Improvements for this road reconstruction and safety project include construction of bike lanes, curbs and gutters, sidewalks, new pavement, installation of street lighting, upgraded and interconnected signalization with pedestrian crossings, construction of a right turn lane on Eastbound South 152nd Street, and the elimination of the skewed intersection at Tukwila International Boulevard and Military Road South. Johansen Construction Company started construction on June 24.
Des Moines Memorial Drive South—South 128th Street to South 136th Street
This project will overlay Des Moines Memorial Drive South from South 128th Street to South 136th
Street. Pavement repair, storm drainage infrastructure, and traffic signal improvements are also included in the scope of work. During the construction period, crews will be shutting down lanes along Des Moines Memorial Drive South between South 128th Street to South 136th Street. Click here for more information.
South 200th Street/Interstate 5 Southbound Metered Shoulder
The City of SeaTac Public Works Department is working in collaboration with the Washington State Department of Transportation to make improvements to the South 200th Street on-ramp. Construction crews will be widening the shoulder along the South 200th Street on-ramp to construct one metered lane and one peak-hour metered lane. In addition, crews will be improving drainage, signage, and lighting, and will also be relocating utilities. Click here for more information.
Des Moines Memorial Drive South and South 200th Street Intersection
Improvements for this intersection include construction of bike lanes, curbs and gutters, sidewalks, new pavement, installation of street lighting, a new traffic signal system with pedestrian crossings, left turn lanes for all approaches, and construction of a right turn lane on westbound South 200th Street. Final design and right-of-way acquisition are in progress. Advertising for construction bids is scheduled for later this summer.
34th Avenue South Project
This “Safe Routes to School” project includes construction of sidewalks, curbs and gutters, storm drainage facilities, installation of an enhanced crosswalk, pedestrian lighting, landscaping, and underground conversion of aerial utilities. Design and right-of-way acquisition are ongoing. Advertising for construction bids for this project is scheduled for December of this year.
South 200th Street Shared-Use Path
This project includes building a new separated shared-use path along South 200th Street between 12th Place South and the Des Moines Creek Trailhead. The project will provide pedestrian connections to street improvements that will be constructed at the intersection of Des Moines Memorial Drive South and South 200th Street, and a connection to existing pedestrian and bicycle facilities accessing the Angle Lake Light Rail Station. Design and right-of-way acquisition are in progress. Advertising for construction bids for this project is scheduled for December of this year.