Traffic Alerts: Nickerson/15th Ave W Ramp Closures for PSE Gas Line Work; Fremont Avenue N tree trimming and road repaving
Fri, 08/19/2011
Nickerson/15th Avenue W ramp:
In preparation for construction to build the Ship Canal Trail, Puget Sound Energy (PSE) will relocate a gas line that runs under the Nickerson/15th Avenue W ramp, just north of W Emerson Street. To complete the work, PSE must close the Nickerson/15th Avenue W ramp to southbound 15th Avenue W from 9 a.m. to 3:30 p.m. each day for up to five days, beginning August 24.The roadway will remain open on weekends, with work resuming August 29 and 30 as needed.
During this utility work PSE will detour most traffic from W Nickerson Street to W Emerson Street heading east, to access southbound 15th Avenue W. Due to the tight turns, large trucks will be detoured onto westbound W Emerson Street, south along Gilman Avenue W to 20th Avenue W, and then eastbound on W Dravus Street to 15th Avenue W.
Seattle Department of Transportation work in the area, to build the Ship Canal Trail, is expected to begin in early September.
Fremont Avenue:
The Seattle Department of Transportation (SDOT) will undertake the following roadway work on Fremont Avenue N, from N 38th to N 41st streets, the week of August 22-26:
-A private contractor will be trimming trees for SDOT on Fremont Ave N, from N 38th to N 41st streets, from 9 a.m. to 3 p.m. on Monday, August 22. Northbound and southbound traffic will be shifted to use the southbound lane and a parking lane. Bicycles will merge with vehicular traffic through the construction zone and all sidewalks will remain open. To assist with traffic flow, a uniformed police officer (UPO) will be stationed at the intersection of N 39th St and Fremont Ave N.
-Following the tree trimming, SDOT crews will be grinding and repaving the travel lanes of Fremont Ave N from N 38th to N 41st streets. This work will occur from 9 a.m. to 5 p.m. on Tuesday, August 23, through Friday, August 26. Northbound and southbound traffic will be shifted to use the parking lanes. Bicycles will merge with vehicular traffic and all sidewalks will remain open. There will be a UPO at the intersection of N 39th St & Fremont Ave N.