Murray CSO Control Project Update: Concrete pours will continue Monday, Jan. 12
Sun, 01/11/2015
information from King County
King County contractors plan to continue pouring the bottom of the underground storage tank on Monday, January 12. Work hours will be 7 a.m. - 6 p.m. Activities at the site will continue past 6 p.m. if necessary to complete work.
On pour days, up to 10 trucks an hour will deliver concrete to the site between 7 a.m. and 6 p.m.
Activities at the site may continue after 6 p.m. if necessary to complete the work.
Two concrete pump trucks on the east side of the 7000 block of Beach Dr. S.W. will pump concrete
into the hole. Crews may continue working in the tank area after 6 p.m. if necessary. Local and
emergency access to Beach Drive S.W. and Lincoln Park Way S.W. will be maintained at all times.
Expect traffic delays and congestion on pour days.
Concrete pours for the underground tank are weather dependent. King County will provide notification via
email in advance of upcoming pours. If you would like to join the email list for the project, please email Doug
Marsano at doug.marsano@kingcounty.gov or call the project hotline at 206-205-9186.
Pour day details:
• Work hours between 7 a.m. and 6 p.m.
Work will continue past 6 p.m. if
necessary to complete the pour.
• Crews working on the east side of Beach
Dr. S.W. near Lowman Beach Park
• Trucks parked on the 7000 block of
Beach Dr. S.W. and Lincoln Park Way
S.W. near Murray Ave. S.W.
• Trucks waiting to deliver concrete will
remain running at all times to expedite
entry to the site
• Flaggers directing traffic along Beach Dr.
S.W. and at the intersection of Beach Dr.
S.W. and Lincoln Park Way S.W.
• No parking in the following locations:
o 7000 block of Beach Dr. S.W.
o Lincoln Park Way S.W. between
Murray Ave S.W. and Beach Dr. S.W.
• Considerable increase in truck traffic
• Traffic delays, congestion around the site
• East sidewalk of Beach Dr. S.W. closed between 7 a.m. and 6 p.m.
Call the 24-hour project information hotline: 206-205-9186