Delridge Way SW & SW Thistle Street intersection will close, April 12-15
Tue, 04/02/2013
Information from SDOT
The Seattle Department of Transportation is in Phase 2 of the project to rebuild much of Delridge Way SW between SW Orchard and SW Roxbury streets. To reduce impacts to the community, intersection construction is taking place on weekends, working around the clock. The next intersection closure is at SW Thistle Street from 7 p.m. Friday, April 12, until 6 a.m., Monday, April 15 at the latest.
Through traffic will be detoured, with local access maintained. Detour information will be available shortly. Meanwhile, most of the in-road work in Phase 1, between SW Henderson and SW Trenton streets, is now complete.
Remaining elements include weather dependent crack sealing work and final roadway markings.
This is a five-phase project.
Phase detours will not take place simultaneously.
Please visit the project website for more information: www.seattle.gov/transportation/pave_delridge.htm