REMINDER: Delridge Way SW & SW Thistle Street Intersection Closure April 12-15
Tue, 04/09/2013
From SDOT:
The Seattle Department of Transportation is in Phase 2 of the project to rebuild much of Delridge Way SW between SW Orchard and SW Roxbury streets. This work is scheduled to close the intersection of Delridge Way SW and SW Thistle Street from 7 p.m. Friday, April 12, until 6 a.m. Monday, April 15 if the weather is dry.
To reduce impacts to the community, intersection construction is taking place on weekends, working around the clock. Through traffic will be detoured, with local access maintained. For the closure of the Delridge/Thistle intersection, the detour will be as follows (see attached map at the top of the story):
· Northbound traffic on Delridge Way SW - Take SW Trenton Street to 35th Avenue SW to SW Holden Street to Delridge Way SW
· Southbound traffic on Delridge Way SW - Take SW Holden Street to 35th Avenue SW to SW Trenton Street to Delridge Way SW
· Westbound traffic on SW Thistle Street - Take 16th Avenue SW to SW Henderson Street to Delridge Way SW
· Eastbound traffic on SW Thistle Street - Take 35th Avenue SW to SW Holden Street or SW Trenton Street to Delridge Way SW
Additionally, there will be a partial closure of the SW Cloverdale Street and Delridge Way SW intersection from 7 a.m. Thursday, April 11, to 5 p.m. Saturday, April 13. This intersection will be closed to eastbound traffic on SW Cloverdale Street on these days. Through traffic will be directed to use a signed detour; local access will be maintained.
This is a five-phase project. Phase detours will not take place simultaneously. At the completion of Phase 2, the construction activity will move to the Phase 3 section of Delridge Way SW, between SW Thistle and SW Holden streets. Please visit the project website for more information: www.seattle.gov/transportation/pave_delridge.htm