Delridge Way SW & SW Thistle St intersection closure has been rescheduled
Thu, 04/11/2013
Information from SDOT
Plans to close and rebuild the Delridge Way SW & SW Thistle Street intersection April 12-15 are now cancelled, due to inclement weather in the forecast. This work is tentatively rescheduled for the weekend of April 26-28, weather permitting.
Also, the partial closure of the SW Cloverdale Street and Delridge Way SW intersection is now expected April 17-19, weather permitting. Eastbound traffic will be rerouted and local access will be maintained.
The Seattle Department of Transportation is in Phase 2 of the five-phase project to rebuild much of Delridge Way SW between SW Orchard and SW Roxbury streets. Phase detours will not take place simultaneously. At the completion of Phase 2, the construction activity will move to the Phase 3, between SW Thistle and SW Holden streets.