Traffic on southbound Delridge Way SW will detour at SW Holden Street
Mon, 05/06/2013
Information from SDOT
The Seattle Department of Transportation expects paving work on Delridge Way Southwest to progress to the next phase on Wednesday, May 15. The contractor will detour southbound traffic on Delridge from Southwest Holden to Southwest Thistle streets, and reopen the stretch from Southwest Thistle to Southwest Trenton streets. The new detour, from Holden to Thistle, is expected to remain in place through mid July. This work is Phase 3 of the project that is rebuilding much of Delridge Way Southwest.
Delridge will remain open to northbound traffic except for intersection work. Local access to businesses and residents will be maintained. SDOT will release a map and details of the new detour as the date approaches.
After the contractor completes work between Thistle and Trenton, Delridge will be striped between Thistle and Henderson streets. Also, crews expect to return by late May to the stretch between Trenton and Henderson for weather-dependent crack seal work.
This is a five-phase project. At the end of the Phase 3, construction activity will move north to Phase 4, between SW Orchard and SW Holden streets.
The Delridge Way SW Paving Project is funded by the Bridging the Gap transportation levy approved by Seattle voters in November 2006.